Our operations

Macleod Flats

Macleod Flats

The Macleod Flats wind facility is located near Fort Macleod, Alberta.

The facility consists of a single Vestas V90 3-megawatt turbine with a 67-metre tower, which was one of the first in North America at the time of installation. The turbine is clearly visible from the town of Fort Macleod.

This single turbine can produce, on average, 9,000 megawatt-hours of electricity each year.

Macleod Flats was commissioned in 2004 and purchased by TransAlta in 2009.

Environmental highlights

The Macleod Flats wind facility has a UL ECOLOGO® Certification for Renewable Energy.

Stats at a glance

TransAlta-operated First on-stream Revenue source TransAlta-built
Yes 2004 Merchant Yes

Facility Image