The Centralia Generating Facility is located in Centralia, Washington. The facility historically operated two coal-fired generating units.
In December 2025, TransAlta announced plans to convert Centralia Unit 2 from coal-fired generation to natural gas-fired generation, subject to regulatory approvals.
The conversion is intended to extend the useful life of the facility while supporting long-term reliability and reducing emissions intensity relative to coal-fired operations.
Further information is available through TransAlta’s public disclosures and a dedicated information page.
Centralia Mining
Coal Combustion Residuals (CCR) rule compliance data and information
The following information is in relation to the Centralia Mining Reclamation activity and is intended to satisfy the requirement under the CCR Rule 40 CFR 257.107 to maintain a publicly accessible internet site (CCR site) containing the required information. The required information will be posted when it is accomplished and is available.
Location restrictions
Unstable areasOperating criteria
CCR fugitive dust control plan Run-on and run-off control planAnnual fugitive dust control report
Annual CCR Fugitive Dust Control Report - 2016 Annual CCR Fugitive Dust Control Report - 2017 Annual CCR Fugitive Dust Control Report - 2018 Annual CCR Fugitive Dust Control Report - 2019 Annual CCR Fugitive Dust Control Report - 2020 Annual CCR Fugitive Dust Control Report - 2021 Annual CCR Fugitive Dust Control Report - 2022 Annual CCR Fugitive Dust Control Report - 2023 Annual CCR Fugitive Dust Control Report - 2024 Annual CCR Fugitive Dust Control Report - 2025Annual engineering inspection reports
CCR Annual Inspection - January 11, 2016 CCR Annual Inspection - January 5, 2017 CCR Annual Inspection - January 4, 2018 CCR Annual Inspection - January 3, 2019 CCR Annual Inspection - January 7, 2020 CCR Annual Inspection - January 6, 2021 CCR Annual Inspection - January 5, 2022 CCR Annual Inspection - January 5, 2023 CCR Annual Inspection - January 3, 2024 CCR Annual Inspection - January 15, 2025 CCR Annual Inspection - January 8, 2026Groundwater monitoring and corrective action
Groundwater monitoring system certification Statistical method certification- Notification of assessment monitoring program
- Notification of return to detection monitoring program
- Notification of Appendix IV exceedances
- Notification of corrective measures assessment
- Corrective measures assessment
- Semi-annual corrective action report
- Notification of completion of corrective action
Reports
Annual groundwater monitoring and corrective action Report – 2017 Addendum to 2017 Annual CCR Groundwater Monitoring Report Annual groundwater monitoring and corrective action Report – 2018 Annual groundwater monitoring and corrective action Report – 2019 Annual groundwater monitoring and corrective action Report – 2020 Annual groundwater monitoring and corrective action Report – 2021 Annual groundwater monitoring and corrective action Report – 2022 Annual groundwater monitoring and corrective action Report – 2023 Annual groundwater monitoring and corrective action Report – 2024 Annual groundwater monitoring and corrective action Report – 2025Closure and post-closure care
Closure plan Post-closure care plan- Time extensions for initiating closure
- Time extensions for completing closure
- Notification of intent to initiate closure
- Notification of completion of closure
- Notification of intent to comply with alternative closure requirements
- Annual progress reports for alternative closure
- Notification recording a notation on property deed
- Post-closure care plan
- Notification of completion of post-closure care
Centralia Generation
Centralia, WA
Energy Transition
Fuel type
670 MW
Gross Installed Capacity
100%
TransAlta ownership